Power Quality Solutions for Data Centers

CHITEK mitigates UPS input harmonics, phase imbalance and reactive swing in data centres using AHF on the UPS feeder and SVG on the mechanical bus. Harmonic current raises transformer temperature and can circulate between parallel UPS units; imbalance loads the neutral. Both are measured in a single survey at the point of common coupling before sizing.

UPS rectifiers, single-phase IT loads and VFD-driven cooling all sit on the same feeder. Harmonic current raises transformer temperature, phase imbalance loads the neutral, and reactive swing from chillers drags power factor down at part load. CHITEK conditions the feeder upstream of the UPS and on the mechanical bus.

Reviewed by the CHITEK power quality engineering team · Last updated

AHF or SVG in a data centre?

Data centres usually separate the two buses: the UPS feeder is a harmonic problem, the mechanical bus is a reactive problem. They are measured and sized independently.

Aspect AHF (Active Harmonic Filter) SVG (Static Var Generator)
What it does Injects a compensating current that cancels the harmonic current drawn by non-linear loads. Supplies or absorbs reactive power continuously to hold power factor and support voltage.
Primary target Current distortion (THDi) and harmonic spectrum at the point of common coupling. Power factor, voltage fluctuation and reactive demand across the load cycle.
Typical trigger VFD banks, rectifiers, welding sets, induction furnaces, LED drivers, UPS rectifiers. Low or swinging power factor, voltage sag and rise, weak or long feeders, EV load steps.
Behaviour at light load Compensation scales with the measured harmonic current, so output falls as load falls. Holds output as required to reach the target power factor even at near-zero active load.
Use in this sector Harmonic correction on the UPS input feeder, where rectifier harmonics circulate between parallel units. Reactive and voltage support on the chiller and CRAC bus, where VFD starting and part-load operation move power factor.

Installing a filter downstream of the UPS output is usually unnecessary, because the UPS already conditions its own output.

Typical power quality problems

Large Cloud Computing Center

HPC / Cloud Provider / Colocation

UPS Harmonics

Reflective pollution from UPS rectifiers

>12%

THD

  • Parallel Circulation — UPS harmonic current circulates between parallel units, load sharing imbalance, thermal runaway risk
  • Battery Life ↓ — Harmonic ripple accelerates VRLA battery corrosion, 3-year life reduced to 18 months

Server Farm

Phase imbalance from single-phase IT load

>15%

Unbalance

  • Neutral Overheat — Triplen + phase imbalance combine, zero-seq > phase current, fire risk
  • PDU Trip — Per-phase overload despite avg below rating, rack PDU breaker nuisance trip, row outage

Cooling System

Reactive impact from VFD chillers/CRAC

PUE

Deterioration

  • Transformer Overload — Excess reactive consumes transformer capacity, forced cooling upgrade, CapEx waste
  • Energy Penalty — PUE 1.6→1.8 from reactive losses, annual OpEx +800K CNY at 10MW facility

Financial Data Center

Bank / Securities / Insurance

High-freq Trading

Sag sensitive trading infrastructure

< 3ms

Sag Tolerance

  • Trade Interrupt — CBEMA/ITIC curve violation, server PSU dropout, millisecond sag = million-yuan loss
  • Regulatory Fine — CSRC trading continuity mandate, outage >5min triggers mandatory reporting, compliance penalty

Diesel Switchover

Transfer shock during genset test/outage

±15%

Voltage Step

  • UPS Overload — ATS transfer inrush, UPS switches to battery, rectifier walk-in overload, system crash
  • Generator Hunting — Load step causes governor oscillation, frequency >2% deviation, PSU shutdown

Precision HVAC

Harmonic source from VFD compressors

>8%

THD

  • PUE Rise — Harmonic derating of cooling xfmrs, reduced cooling capacity, hot spot in racks
  • Control Fault — Harmonic noise on HVAC controller PSU, sensor drift, temperature oscillation

Edge Computing Node

5G Base / IoT / Distributed Room

Grid Quality

Unstable supply at remote/rural sites

>20%

Sag Depth

  • Node Offline — Frequent sag triggers mini-UPS battery discharge, cycle life exhausted within 6 months
  • Truck Roll Cost — Each site visit costs 800 CNY, 200+ nodes = 160K CNY/month O&M overhead

Small UPS

Overload risk at single-cabinet sites

>80%

Load Ratio

  • No Redundancy — N config, single UPS failure = complete node outage, SLA 99.9% breached
  • Battery Overheat — High charge rate in compact cabinet, thermal runaway, fire risk in unattended sites

Distributed Load

Phase imbalance from single-phase 5G/IoT

>10%

Unbalance

  • Efficiency Loss — DER coordination failure, negative-seq current, PCS derating 15%, curtailment
  • Single-phase Trip — Per-phase overcurrent, cascade trip of co-located equipment on same feeder

Data Center case studies

Each case below is written up the same way: what the site was, what the survey measured before anything was specified, what was installed, and what the acceptance test showed afterwards. Projects marked Typical Configuration are illustrative — sizing for those always starts from a site survey rather than from the table.

UPS Harmonic Mitigation on a Data Centre Feeder, Guangzhou

Colocation / IDC

UPS Harmonic Mitigation on a Data Centre Feeder, Guangzhou

Harmonic current 204.96 A → 19.18 A; distortion 26.94% → 3.12%

Background

The TR1 feeder of an IDC hall, running between 200 A and 850 A with a displacement power factor of 0.975 before the retrofit. The existing filter cabinet was rebuilt rather than replaced.

What we measured

  • Load current 814.13 A at 82% load factor
  • Total harmonic current 204.96 A, Ithd 26.94%
  • Displacement power factor 0.975 before the retrofit
  • Per-phase distortion after treatment: 3.12% / 2.50% / 2.55% on A / B / C

Equipment installed

  • AHF-500A
    AHF-500A × 1 units Active Harmonic Filter Rebuilt filter cabinet on the TR1 feeder

Project overview

TR1 feeder of an IDC hall, running current 200–850 A, displacement power factor 0.975 before retrofit. The existing filter cabinet was rebuilt around a new 500 A active filter. At 814.13 A load current (82% load factor) the measured harmonic current peaked at 204.96 A with 26.94% distortion.

Before / After

Harmonic current 204.96 A → 19.18 A · Distortion 26.94% → 3.12%

Key results

  • Phase-level distortion 3.12% / 2.50% / 2.55% on A / B / C
  • Power factor held at 0.981 in service
  • Every harmonic order within GB/T 14549 limits
  • IDC hall phases I and III passed fire-inspection filing

Scope and limitations

Covers one feeder of the hall, not the whole site. The figures are taken at 814.13 A load current (82% load factor), which is the point the commissioning report used for acceptance.

Frequently asked questions

Where should an AHF be installed in a data centre?

At the feeder upstream of the UPS, or on the mechanical bus feeding chillers and CRAC units. Installing downstream of the UPS output is possible but usually unnecessary, because the UPS already conditions its own output.

Does harmonic filtering improve PUE?

Indirectly. Harmonic current causes extra loss in transformers and cables and can force a transformer to run hotter than designed, so removing that current reduces those losses. PUE depends on the whole mechanical and electrical design, so the effect has to be measured rather than assumed.

Is phase imbalance a separate problem from harmonics?

Yes. Single-phase IT loads spread unevenly across the phases create negative-sequence and zero-sequence current. Harmonics are a waveform problem, imbalance is a distribution problem, and both are normally measured in the same survey.

Can edge sites with small UPS systems use the same equipment?

Yes, in smaller ratings. Remote and rural edge nodes often have worse supply quality than a core data centre, so the survey step matters more there, not less.

Related products

Solutions for other industries

Get a power quality assessment for your site

Every project on this page started with a measured survey. Send us your single-line diagram and load list and we will tell you what we would measure first.

Contact our engineers