Power Quality Solutions for Industrial Manufacturing

CHITEK conditions harmonic and reactive problems on industrial plant feeders using active harmonic filters (AHF) and static var generators (SVG). The usual triggers are VFD banks, welding equipment and induction furnaces. Sizing follows a measured harmonic spectrum at the point of common coupling, not the transformer rating alone.

Welding banks, induction furnaces, CNC servo drives and large VFD installations all inject harmonic current back into the plant feeder. The result is transformer overheating, recurring capacitor failures and unstable process equipment. CHITEK active harmonic filters (AHF) and static var generators (SVG) are installed at the transformer or at the feeder to bring distortion back inside the plant limits.

Reviewed by the CHITEK power quality engineering team · Last updated

AHF or SVG for a manufacturing plant?

Most industrial sites start by identifying which of the two problems is dominant. Distortion and reactive demand are measured separately in the survey, and either can be the binding constraint.

Aspect AHF (Active Harmonic Filter) SVG (Static Var Generator)
What it does Injects a compensating current that cancels the harmonic current drawn by non-linear loads. Supplies or absorbs reactive power continuously to hold power factor and support voltage.
Primary target Current distortion (THDi) and harmonic spectrum at the point of common coupling. Power factor, voltage fluctuation and reactive demand across the load cycle.
Typical trigger VFD banks, rectifiers, welding sets, induction furnaces, LED drivers, UPS rectifiers. Low or swinging power factor, voltage sag and rise, weak or long feeders, EV load steps.
Behaviour at light load Compensation scales with the measured harmonic current, so output falls as load falls. Holds output as required to reach the target power factor even at near-zero active load.
Use in this sector Feeder-level harmonic correction at the transformer or at the main incomer feeding VFD and furnace loads. Reactive support where power factor penalties apply or where furnace switching causes voltage fluctuation.

Ratings are set from the survey. Where a plant runs both VFD banks and furnaces, the two devices are normally combined rather than sized as alternatives.

Typical power quality problems

Welding & Metal Processing

Automotive / Shipbuilding / Steel Structure

Arc Welder Bank

Harmonic surge from batch arc welding

>25%

THD

  • Transformer Overheat — Intermittent high harmonic current, insulation aging accelerated 3x, forced derating
  • Protection Trip — Harmonic peak triggers breaker false trip, production line stoppage, rework cost

Medium Freq. Furnace

Voltage flicker from induction furnace

Reactive

Fluctuation

  • Grid Voltage Sag — Furnace cycle causes Pst > 1.5, neighboring equipment malfunction, batch rejection
  • Penalty Fee — Utility flicker violation, monthly reactive energy surcharge, contract non-compliance

CNC Machining Center

Phase imbalance from servo drives

High

Zero-seq.

  • Servo Malfunction — Phase imbalance causes position error, workpiece dimensional drift, scrap rate increase
  • Yield Loss — Frequent tool breakage, surface finish degradation, customer return rate surge

Chemical & Petrochemical

Refining / Fine Chemical / Oil & Gas

VFD Bank

Harmonic stacking from multi-VFD installation

>18%

THD

  • Grid Violation — Multi-VFD harmonic overlay, IEEE 519 PCC limit exceeded, utility warning notice
  • Capacitor Trip — Harmonic amplification in PFC capacitors, fuse blowing, reactive penalty escalation

High-power Pump

Startup surge from large motors

6~10x

Inrush

  • Bus Voltage Dip — DOL start causes 20%+ bus dip, DCS I/O module brownout, control loop instability
  • DCS Alert — Repeated sag triggers DCS alarm flood, operator cognitive overload, response delay

DCS System

Sag sensitive control infrastructure

>15%

Sag Depth

  • Control Freeze — Sag causes DCS processor reset, valve position loss, exothermic reaction risk
  • Process Stop — Safety instrumented system triggers ESD, batch loss, 48hr restart procedure

Semiconductor & Electronics

Wafer Fab / Packaging / PCB

Wafer Fab

Voltage sag at lithography scanners

< 5ms

Sag Tolerance

  • Scanner Halt — Sub-cycle sag causes scanner stage position loss, 4hr recalibration, wafer scrap
  • Wafer Scrap — Single sag event = 25 wafers scraped × $5K/wafer = $125K loss per incident

Cleanroom

Harmonic pollution from FFU/VFD

>8%

THD

  • Filter Load ↑ — Harmonic current increases FFU motor temperature, bearing failure rate 3x, particle count rise
  • Particle Risk — FFU speed fluctuation causes positive pressure loss, Class-100 cleanroom breach

Test Equipment

Phase imbalance at ATE/test floor

>5%

Unbalance

  • Data Error — ATE power supply ripple rejection degraded, false DUT rejection, yield reporting error
  • Neutral Overheat — High zero-seq current in test floor PDU, N-line temp > 90°C, fire risk

Industrial case studies

Each case below is written up the same way: what the site was, what the survey measured before anything was specified, what was installed, and what the acceptance test showed afterwards. Projects marked Typical Configuration are illustrative — sizing for those always starts from a site survey rather than from the table.

Harmonic Retrofit on a 550 A Plant Feeder — Electronics Manufacturer, Guangdong

Electronics Manufacturing

Harmonic Retrofit on a 550 A Plant Feeder — Electronics Manufacturer, Guangdong

Current distortion 20.06% → 2.58% on a VFD / compressor / pump feeder

Background

Feeder TM8 at an electronics manufacturing plant, supplying variable-frequency drives, air compressors and cooling water pumps. The circuit already carried 390 kvar of capacitor compensation within a 780 kvar installed bank, and ran between 800 A and 1,000 A at a system power factor of 0.92.

What we measured

  • Running current 800–1,000 A on feeder TM8
  • Current distortion 20.06% before the retrofit
  • System displacement power factor 0.92
  • 390 kvar of capacitor compensation on the circuit, 780 kvar installed

Equipment installed

  • AHF-550A
    AHF-550A × 1 units Active Harmonic Filter Harmonic compensation on feeder TM8

Project overview

Feeder TM8 supplies VFDs, air compressors and cooling water pumps, with 390 kvar of capacitor compensation on the circuit (780 kvar installed). Running current 800–1,000 A, system displacement power factor 0.92 before retrofit.

Before / After

Distortion 20.06% → 2.58%

Key results

  • Current distortion 20.06% → 2.58%
  • Harmonic amplification and system resonance avoided
  • Accepted on test against GB/T 14549

Scope and limitations

Results are reported for the TM8 feeder only. Other feeders at the same plant were not part of this contract and are not covered by the figures.

Frequently asked questions

What causes harmonics in a manufacturing plant?

Non-linear loads: rectifiers in VFDs and servo drives, arc welders, induction melting furnaces and DC power supplies. They draw current in short pulses rather than as a sine wave, and those pulses appear as harmonic current on the feeder.

Can an active harmonic filter run alongside an existing capacitor bank?

Yes, but where the filter CTs sample matters. If the CTs are on the grid side and the connection point sits downstream of a pure capacitor bank, the filter can excite LC resonance. Use selective filtering orders with anti-resonance control, or move CT sampling to the load side.

Do I need an AHF, an SVG, or both?

An AHF cancels harmonic current. An SVG supplies or absorbs reactive power and holds power factor. If the problem is distortion, start with AHF. If it is low power factor or voltage fluctuation, start with SVG. Plants running both VFD banks and furnaces often need both.

How is filter capacity sized?

From a power quality survey at the point of common coupling: measure the harmonic spectrum, the reactive profile and the load cycle. Sizing from transformer kVA alone is the most common reason an installation ends up undersized.

Related products

Solutions for other industries

Get a power quality assessment for your site

Every project on this page started with a measured survey. Send us your single-line diagram and load list and we will tell you what we would measure first.

Contact our engineers